Para 9.4 - Inordinate Delays | KartavyaDesk
Original Rule Text
4. Inordinate Delays: Inexcusable delays of more than one-fourth (25%) of the total completion period shall be treated as inordinate delays. Such inordinate delays may be treated as breach of contract and shall be noted as deficient performance and be held against the contractor in future tenders. A show-cause notice shall be issued to the contractor before declaring it a deficient performance. In case Procuring Entity decides to allow performance of contract, after inordinate delays, maximum limit on LD shall be 10% (instead of 5%) of the total contract value, as per para 9.4.7-1 and 9.4.9 below.
What This Means
Para 9.4 of the Manual for Procurement of Non-Consultancy Services deals with what happens when a contractor significantly delays completing a project. Specifically, if the delay exceeds 25% of the total time originally agreed upon for the project, it's considered an 'inordinate delay.' This is a serious issue because it can be seen as a breach of contract and will negatively impact the contractor's chances of winning future government tenders. Before labeling the performance as deficient, the government agency must issue a show-cause notice to the contractor, giving them a chance to explain the delay.
If, despite the delay, the government agency decides to allow the contractor to continue and complete the project, there's a change in the penalty for further delays. Normally, the Liquidated Damages (LD), which is a penalty for delays, is capped at 5% of the total contract value. However, in cases of inordinate delay where the agency allows the contract to continue, the maximum LD that can be charged is increased to 10% of the total contract value. This increased penalty serves as a stronger incentive for the contractor to complete the project as quickly as possible.
This explanation was generated with AI assistance for educational purposes. Always refer to the official gazette notification for authoritative text.
Key Points
- •Inordinate delay is defined as exceeding 25% of the total completion period.
- •Inordinate delay can be treated as a breach of contract and results in deficient performance record.
- •A show-cause notice must be issued to the contractor before declaring deficient performance.
- •If the procuring entity allows the contract to continue after inordinate delay, the maximum Liquidated Damages (LD) increases from 5% to 10% of the contract value.
Practical Example
The Municipal Corporation of Delhi (MCD) awarded a contract to 'CleanSweep Pvt. Ltd.' to clean a specific area of the city within 100 days for a total contract value of ₹50 Lakhs. CleanSweep faced unexpected equipment breakdowns and labor shortages, causing a delay of 30 days. This 30-day delay exceeds 25% of the original 100-day timeline, making it an inordinate delay.
The MCD issued a show-cause notice to CleanSweep, who explained the reasons for the delay. After considering the explanation, the MCD decided to allow CleanSweep to continue the project. However, because of the inordinate delay, the maximum Liquidated Damages that the MCD could now impose for any further delays is 10% of the ₹50 Lakhs contract value, i.e., ₹5 Lakhs, instead of the usual 5% (₹2.5 Lakhs). This motivates CleanSweep to complete the project as quickly as possible to avoid further penalties.
This explanation was generated with AI assistance for educational purposes. Always refer to the official gazette notification for authoritative text.
Frequently Asked Questions
What constitutes 'total completion period' in this context?▼
What happens if the contractor doesn't respond to the show-cause notice?▼
Does this rule apply to all types of government contracts?▼
Can the procuring entity reduce the LD back to 5% if the contractor improves performance after the inordinate delay?▼
What is the purpose of issuing a show-cause notice?▼
This explanation was generated with AI assistance for educational purposes. Always refer to the official gazette notification for authoritative text.
Test Your Knowledge
Question 1 of 3
According to Para 9.4 of the Manual for Procurement of Non-Consultancy Services, an 'inordinate delay' is defined as a delay exceeding what percentage of the total completion period?
Related Rules
Need help understanding this rule?
Ask Niti — your AI assistant for Non-Consultancy Manual and other government rules