Original Rule Text
a) “Deviation” is a departure from the requirements specified in the Tender Document; b) “Reservation” is the setting of limiting conditions or withholding from complete acceptance of the requirements specified in the Tender Document. c) “Omission” is the failure to submit part, or all of the information or documentation required in the Tender Document.
2. Substantive Deviations: A deviation/ reservation/ omission from the requirements of the Tender Document shall be considered a substantive deviation as per the following norm, and the rest shall be considered a Minor deviation:
a) Which affects in any substantive way the scope, quality, or performance of the product; b) Which limits in any substantive way, inconsistent with the Tender Document, the Procuring Entity's rights, or the Bidder's obligations under the contract; or c) Whose rectification would unfairly affect the competitive position of other Bidders presenting substantively responsive Bids.
3. The decision of the Procuring Entity shall be final in this regard. Bids with substantive deviations shall be rejected as nonresponsive. However, bids with deviations may accepted in case of STE/ PAC procurement with approval of Competent Financial Authority, with reasons recorded for accepting such deviations.
4. Variations and deviations and other offered benefits (techno-commercial or financial) above the scope/ quantum of the Goods specified in the Tender Document shall not influence evaluation Bids. If the bid is otherwise successful, the Procuring Entity shall avail of such benefits, and these will become part of the contract.
5. During the preliminary examination, some minor infirmity and/or irregularity and/or nonconformity may also be found in some bids. Such minor issues could be missing pages/attachments, illegibility in a submitted document, or non-submission of the requisite number of copies of a document.
7.3.4 Deviations/ Reservations / Omissions - Substantive or Minor 1. During the evaluation of Bids, the following definitions apply:
7.3.5 Clarification of Bids/Shortfall Documents 1. During the evaluation and comparison of bids, the purchaser may, at his discretion, ask the bidder for clarifications on the bid. The request for clarification shall be given in writing by registered/ speed post/ courier/ email, asking the bidder to respond by a specified date, mentioning therein that if the bidder does not comply or respond by the date, his tender will be liable to be rejected. Depending on the outcome, such bids are to be ignored or considered further. No change in prices or substance of the bid, which may grant any undue advantage to such bidder, shall be sought, offered, or permitted. No post-bid clarification at the initiative of the bidder shall be entertained.
6. Considering Minor Deviations: There have also been cases where the bidder submitted the amendment Bank Guarantee but omitted to submit the main portion of the document. The court ruled that this was a minor irregularity. The court has consistently taken the view that the procuring entity is entitled to consider and allow minor deviations that do not amount to substantive deviations. The Procuring Entity reserves the right to accept bids with such minor issues provided they do not constitute any substantive deviation, do not have a fiscal impact, do not prejudice, or affect the ranking order of the bidders and do not grant the bidder any undue advantage vis-à-vis other bidders and the Procuring Entity. Wherever necessary, the Procuring Entity shall convey its observation on such ‘minor’ issues to Bidder as per para 7.3.5 below. If the Bidder does not reply by the specified date or gives an evasive reply without clarifying the point at issue in clear terms, that bid shall be liable to be rejected as nonresponsive.
2. The Procuring Entity reserves its right to, but without any obligation to do so, seek any shortfall information/ documents only in case of historical documents that pre-existed at the time of the Bid Opening, and which have not undergone change since then and does not grant any undue advantage to any bidder. Provision may be made by e-Procurement portals for requesting Short-fall documents from the bidders. The system may further allow shortfall documents to be taken from any bidders only once after the technical bid opening. (Example: if the Permanent Account Number, registration with GST has been asked to be submitted and the bidder has not provided them, these documents may be asked for with a target date as above). As far as the submission of documents is concerned regarding qualification criteria, after submission of the bid, only related shortfall documents should be asked for and considered. For example, if the bidder has submitted a supply order without its completion/performance certificate, the certificate can be asked for and considered. However, no new supply order should be asked for to qualify the bidder.