Para 6.5 — GOODS_MANUAL
Original Rule Text
2. Quantum: The quantum of such advance payments should not exceed the quantum of funds to be sunk by the contractor before payment becomes due in the contract. The quantum of advance payments should not generally exceed the following limits:
a) Thirty per cent of the contract value to private firms; b) Forty per cent of the contract value to a state or central Government agency or PSE; c) In the case of the maintenance contract, the amount should not exceed the amount payable for six months under the contract. d) In exceptional cases, the competent authority may relax the ceilings mentioned above with prior concurrence of the Associated/Integrated Finance.
3. Interest-free: Since the provision of advance payment leverages the difference in interest rate as argued in sub-para 1) above and considering the additional cost of Bank Guarantee for advances for the bidder, interest-free advance payments may be considered with the approval of competent authority and finance concurrence. Where an interest-free advance is permitted, a clause in the tender enquiry and the contract may be stipulated that if the contract is terminated due to default of the contractor, the advance payment would be deemed as an interest-bearing advance at the interest rate (e.g., the interest rate of the General Provident Fund – GPF) prevailing on the date of release of advance payment, plus 2% to be compounded quarterly. In appropriate cases, the competent authority may stipulate advance payments with suitable interest rates (e.g., the interest rate of the General Provident Fund – GPF) to be recovered along with the instalments of recovery of advance payment.
6.5. Advance Payment (Rule 172(1) GFR 2017) 6.5.1 Conditions for Advance Payments 1. Conditions: Ordinarily, payments for services rendered or supplies made should be released only after the services have been rendered or supplies made. However, in exceptional situations where substantial funds are to be sunk by the contractor before payment becomes due, considering the lower cost of funds for the Government entity as compared to the higher cost of funds for the bidder, advance payment with safeguards (BG or Insurance Surety Bond or Letter of Credit) may be considered. So advance payments may be considered only in the following exceptional situations: a) Advance payment demanded by firms holding maintenance contracts for servicing of air-conditioners, computers, other costly equipment, etc.; b) Advance payment demanded by firms against fabrication contracts, turn-key contracts, or supply of complicated tailor-made goods and so on;
6.5.2 Documents for Advance Payments Documents needed from the supplier for advance payment release are to be clearly specified in the contract. The paying authority should also verify the documents received from the supplier with corresponding stipulations made in the contract before releasing the payment.
4. Instalments: The advance payment should not be made in less than two instalments, as per the expected infusion of funds required in the contract, except in exceptional circumstances for the reasons to be recorded. This will keep a check on contractor misutilisation of full advance when the contract is delayed considerably.
5. Recovery: Advance payments, especially interest-free advances, should be recovered (from either running bills or from the Performance/ Advance payment Bank Guarantees) in instalments linked to milestones or specified periods, whichever is earlier. This would ensure that even if the contractor is not executing the work or executing it at a slow pace, recovery of advance could commence, and the scope for misuse of such advance could be reduced. 6. Bank Guarantee: While making any advance payment as above, adequate safeguards in the form of a bank guarantee (or e-Bank Guarantee of at least 110% of advance) should be obtained from the firm. In case the advances are to be paid/ recovered in instalments, an equal number of part BGs (with proportionate amount and validity) may be taken instead of lumpsum BG, with each BG released after a related recovery is made. An Indemnity Bond is not to be considered in place of a Bank Guarantee. However, no Bank Guarantee should be insisted in case advance is being given to Central Ministry/ Department, there attached/ subordinate offices or the Autonomous Bodies attached with them. The BG may also not be taken, wherever a contract has been placed on a CPSE on nomination basis. 7. Milestone/ stage payments or part payments against proof of dispatch documents should not be considered as advance payments for the purpose of this para, as these payments are made after the sinking of funds by the contractor for achieving these milestones/ stage/ dispatches. These should be provisioned in the tender document/ contract, including Bank Guarantee to be taken, if any, in case of milestone/ stage payments. (Rule 172(2) GFR 2017) 8. Provision of advance payment should be anticipated at the procurement planning stage. The quantum of Advance payment and related conditions should be declared in the Tender Documents, with the approval of competent authority and concurrence of associated/ integrated finance. If not so declared, the condition of advance payment for a particular bid should not be agreed to.