Rule 269 Fund flow for Central or Central sponsored Projects. Under the Central or Central sponsored project financed from external aid, whether loan or grant, the process of disbursement of such claims by the Funding Agency shall be the same as explained in Rule 267. The respective Ministry or Department get EAP funds under a separate budget head when Demands for Grants are passed in the Parliament and advised by the Budget Division of the Ministry of Finance. The funds shall be released to Project Implementing Agency within six weeks by the administrative Ministry or Department with reference to expenditure incurred by the Project Implementing Agency.