Para 6.5 - Price Variation Clause | KartavyaDesk
Original Rule Text
d) Essential elements of PVC: i) Base Date & Time Lag: The price agreed upon should specify the base date, that is, the month and year to which the contract/ bid price is linked, to enable variations to be calculated with reference to the price indices prevailing in that month and year. This base date should be a few weeks/ months (the period is called time-lag) prior to the last date of submission of bids when the last published price indices would be available. Time lag applies both for the base date and delivery date and must be specified in the Tender Documents; ii) Ignorable Variation: The price variation formula must also stipulate a minimum percentage of variation of the contract price, only above which the price variation will be admissible (for example, where the resultant increase is lower than, say, two per cent of the contract price, no price adjustment will be made in favour of the contractor); iii) Inordinate Variation: In rare cases, prices may go up to such an extent that it may render the contract unviable for either party, thus frustrating the contract. Therefore, the price variation clause should provide for a ceiling (a percentage per annum or an overall ceiling or both, say 20%/ 25% of the original price) on price variations, beyond which the price variation would be capped at this level. As soon as it comes to light that price variations are likely to go beyond this ceiling, and if the Contractor is not agreeable to the price variation being capped at that level, he may notify the Purchaser under ‘Frustration of Contract’ provisions in the Tender Document/ Clause, for short-closing the contract. (Refer para 10.8.5). However, if the short closing is not in the interest of the procuring entity, the competent authority, with the concurrence of associated/ integrated finance, may allow the continuation of the contract by relaxing/ removing the cap on the price variation. iv) Where advance or stage payments are made, there should be a further stipulation that no price variations will be admissible on such portions of the price after the dates of such payment; v) Where deliveries are accepted beyond the scheduled delivery date subject to levy of liquidated damages as provided in the contract. The LD (if a percentage of the price) will be recoverable on the price as varied by the operation of the PVC; vi) No upward price variation will be admissible beyond the originally scheduled delivery date for defaults on the part of the contractor (e.g., when an extension
What This Means
Para 6.5(d) of the Manual for Procurement of Consultancy Services outlines the essential elements of a Price Variation Clause (PVC). A PVC is a part of the contract that allows the price to be adjusted based on changes in market conditions, like inflation or fluctuations in material costs. This clause is crucial for long-term consultancy contracts where costs can change significantly over time. It aims to protect both the government and the consultant from unforeseen economic shifts. This section ensures that the PVC is fair, transparent, and prevents either party from being unfairly disadvantaged by price fluctuations.
This explanation was generated with AI assistance for educational purposes. Always refer to the official gazette notification for authoritative text.
Key Points
- •Base Date & Time Lag: The contract must specify a base date and time lag to link the price to a specific point in time for accurate variation calculations.
- •Ignorable Variation: A minimum percentage of price variation must be stipulated, below which no price adjustment will be made.
- •Inordinate Variation: A ceiling (percentage per annum or overall) should be set on price variations to prevent contracts from becoming unviable.
- •Advance/Stage Payments: No price variations are allowed on portions of the price already paid as advance or stage payments.
- •Liquidated Damages (LD): If deliveries are delayed and LD is applied, the LD is calculated on the price after variation.
Practical Example
The Ministry of Urban Development hires 'City Solutions Pvt. Ltd.' for a 3-year urban planning consultancy project. The contract includes a PVC with a base date of January 2024 and a time lag of 2 months. It also specifies that price variations will only be considered if they exceed 3% of the contract price. Furthermore, the PVC includes a ceiling of 20% per annum on price variations. After one year, inflation causes a significant increase in consultant salaries and operational costs. City Solutions requests a price variation. The Ministry reviews the request, calculates the variation based on the agreed formula, and approves an adjustment within the 20% ceiling. However, no variation is allowed on the 20% advance payment already made at the start of the project.
This explanation was generated with AI assistance for educational purposes. Always refer to the official gazette notification for authoritative text.
Frequently Asked Questions
What is the purpose of having a 'base date' in the PVC?▼
Why is there a need for an 'ignorable variation' clause?▼
What happens if the price variation exceeds the stipulated ceiling?▼
How does the PVC affect liquidated damages?▼
Are price variations allowed on advance payments?▼
This explanation was generated with AI assistance for educational purposes. Always refer to the official gazette notification for authoritative text.
Test Your Knowledge
Question 1 of 3
According to Para 6.5(d) of the Manual for Procurement of Consultancy Services, what is the purpose of specifying a 'base date' in a Price Variation Clause (PVC)?
Related Rules
Need help understanding this rule?
Ask Niti — your AI assistant for Consultancy Manual and other government rules