Para 2.3 — CONSULT_MANUAL
Original Rule Text
2. Hence ToR should be comprehensive and unambiguous. However, it should not be too detailed and inflexible, so that competing consultants may be in a position to propose their own methodology and staffing. Bidders shall be encouraged to comment on the ToR in their proposals. The ToR shall include:
a) Procuring Entity’s organisation background and Project background; b) Purpose and Service Outcomes Statement of the assignment; (refer to chapter 1) c) Detailed scope of work Statement including schedule for completing the assignment; d) Expected requirement of key professionals and kind of expertise; e) Capacity-building programme and transfer of knowledge, if any; f) Deliverables - List of reports (or documents, data, maps, surveys, designs, drawings), schedule of deliveries, and period of performance; g) Background material, Data, reports, records of previous surveys, and so on, available and to be provided to the consultant; h) Facilities such as local conveyance, office space, office machines, secretarial assistance, utilities, local services, etc., which would be provided to the consultant by the Procuring Entity; i) Institutional and organisational arrangement; and
2.3 Preparation of Terms of Reference (ToR) 1. ToR is akin to Description, Quantity and Technical Specification in Procurement of Goods. This is the first step in the selection of the consultants once a need has been identified. It explains the purpose/ objectives of the assignment, scope of work, activities, tasks to be performed, respective responsibilities of the Procuring Entity and consultant, expected results, and deliverables of the assignment. It is important for an understanding of the assignment and its correct execution to ensure that the objectives of assignment are achieved. It reduces the risk for the Procuring Entity of unnecessary extra work, delays, and additional expenses. In addition, it helps reduce for the bidders the risk of ambiguities during the preparation of bidder’s proposals, contract negotiation, and execution of Consultancy.
Manual for Procurement of Consultancy Services, Second Edition, 2025 j) Procedure for review of the work of consultant after award of contract 3. A template for developing a ToR is given at Annexure 4. It should cover following aspects: a) Detailed Scope of Work: As part of the ToR, at its simplest, the 'Detailed Scope of Work ' will contain the type and volume of activity to be undertaken and the timeframe of activity involved to achieve the Purpose and Service Outcomes as envisage in the 'Brief proposal and Justification of the Services' (refer chapter 1). Starting from end-outcomes backwards, the process to achieve the outcomes is broken down into a discrete number of interrelated tasks, which the consultant will have to undertake. In consultancy Services, the 'Detailed Scope of Work’ should describe only the activities, not the approach or methodology by which the results are to be achieved, since these are the task of the consultants. However, suggestions may be provided on the approach or the methodology that the consultants could or should use to execute the assignment. After the tasks are identified, a logical sequencing of the tasks must be determined. Usually a simple bar chart (or Gantt-chart) is the best way to illustrate required outputs over time and their relationship to each other. The 'Detailed Scope of Work ' contains such a sequence of tasks over a timeline and also tangible outputs and activities such as reports, workshops, or seminars. b) Expected requirement of key professionals and kind of expertise” Except in very complex Consultancies, it is desirable to not to distinguish the tasks of individual experts but instead to prepare a longer and more detailed description of what the Consultancy team, as a whole, will provide without splitting up tasks. These are generally known as “activity based” ToR as opposed to “position-based” ToR. The ToR would list a range of tasks without regard to who will have the responsibility to undertake them. In most of the cases, where the number of experts is small, the work to be done is not clearly defined, and a degree of flexibility is required— this is acceptable. In Consultancy services, Key professionals are usually named, and their credentials carry weightage in technical evaluation. c) Deliverables and Reports Requirements: The assignments deliverables and reporting should be clearly specified. In particular, for inception and progress reports, there should be a balance between keeping the Procuring Entity well informed and not forcing consultants to spend an excessive amount of time preparing minor reports. The ToR should indicate the format, frequency, and content of reports as well as the number of copies, the language, and the names of the prospective recipients of the reports. For all major reports, an executive summary is recommended as a separate section. Depending on the assignment, the following reports are usually required; i) Inception Report: This report should be submitted about six weeks after the commencement date. Any major inconsistency in the ToR, staffing problems, or deficiency in Procuring Entity’s assistance that have become apparent during this period should be included. The inception report is designed to give the Procuring Entity confidence that the assignment can be carried out as planned and as agreed upon in the contract and should bring to its attention major problems that might affect the direction and progress of the work. ii) Progress Reports: These reports keep the Procuring Entity regularly informed about the progress of the assignment. They may also provide warnings of anticipated problems or serve as a reminder for payment of invoices due.
Chapter 2: Need assessment and Procurement Planning Depending on the assignment, progress reports may be delivered monthly or bimonthly. For feasibility studies and design assignments, delivery of progress reports at two-month intervals is satisfactory. For technical assistance and implementation supervision, for instance, construction, progress reports are best submitted monthly. Progress reports may include a bar chart showing details of progress and any changes in the assignment schedule. Photographs with timestamping are a quick and easy way of conveying the status of a project, and their use in progress reports should be encouraged. For technical assistance services, progress reports also serve as a means of setting out the work program for the following months. Each team member usually contributes to the preparation of the monthly report. iii) Interim Reports: If the assignment is phased, interim reports are required to inform the Procuring Entity of preliminary results, alterative solutions, and major decisions that need to be made. Since the recommendations of an interim report may affect later phases of the assignment and even influence the results of the project, the Procuring Entity should discuss the draft interim reports with consultants in the field. The Procuring Entity should not take more than 15 (fifteen) days to review and approve draft interim reports. iv) Final Report: The final report is due at the completion of the assignment. The Procuring Entity and consultants should discuss the report while it is still in draft form. The consultants alone are responsible for their findings; although changes may be suggested in the course of the discussions, consultants should not be forced to make such changes. If the consultants do not accept comments or recommendations from the Procuring Entity, these should be noted in the report. The consultants should include in the report the reasons for not accepting such changes. d) Background material, records of previous surveys etc. available and to be provided to the consultant. This would vary from project to project, but transparency demands that such information should be transparently and equitably shared with all prospective bidders. e) Facilities such as local conveyance, office space, secretarial assistance etc., which can be provided to the consultant. This aspect has a great bearing on the cost that will be quoted by the bidders. This can have implications in vitiating the selection process either way – a facility to be provided may not get declared or a declared facility may not be provided ultimately. So, great care and reality check is necessary, while preparing this statement. f) Procedure for review of the consultancy after award of contract: In consultancy services, the Contract Monitoring Committee (CMC), and procedure for review and approval of work of the consultant after the award of contract should also be declared and adhered to.
(Rule 185 of GFR 2017)